Pick Activity in BPEL
This activity waits for the occurrence of one event in a
set of events and performs the activity associated with that event. The
occurrence of the events is often mutually exclusive (the process either
receives an acceptance or rejection message, but not both).
If multiple events
occur, the selection of the activity to perform depends on which event occurred
first. If the events occur nearly simultaneously, there is a race and the
choice of activity to be performed is dependent on both timing and
implementation.
The pick activity provides an OnMessage branch.
When you
double-click the OnMessage icon in BPEL 1.1, the dialog shown in Figure A-24
appears.
In BPEL 2.0, the OnMessage dialog
includes a Documentation tab and does not include a Skip Condition
tab or an Assertions tab.
The two branches of the pick activity
are as follows:
Contains the code for receiving a reply, for example, from a loan service.
·
onAlarm (does
not automatically display; you must manually add this branch by selecting the Pick
activity icon and clicking the Add OnAlarm icon)
Contains the code for a timeout, for example, after one minute.
Whichever branch completes first is executed; the other
branch is not executed. The branch that has its condition satisfied first is
executed.
Figure A-25
shows the OnAlarm dialog of the pick activity in BPEL 1.1.
In BPEL 2.0, the OnAlarm dialog includes a Documentation
tab and does not include a Skip Condition tab.
Note:
You can also create onMessage branches in BPEL 1.1 scope activities and
onAlarm branches in BPEL 1.1 and 2.0 scope activities. Expand the Scope
activity in Oracle JDeveloper, and browse the icons on the left side to find
the branch you want to add.
If you add correlations to an OnMessage
branch, the correlations syntax is placed after the assign activity
syntax. The correlation syntax must go before the assign activity.
As a work around, perform the following steps:
1.
Create a correlation set in Oracle
JDeveloper.
2.
Assign this to the OnMessage branch.
3.
Complete the remaining design tasks.
4.
Before making or deploying the BPEL
process, move the correlation syntax before the assign activity in the BPEL
source code.